In the previous post I briefly explored the use of downscoping in the project context, both as a tool for controlling budgets and schedules, and as a means of inflicting damage on one's political rivals. Although downscoping can be effectively abused for political purposes, there are still other reasons to question its effectiveness in controlling projects.
The fundamental limitations of downscoping as a project control measure arise from the difficulty of managing the decision-making processes used to determine which objectives to cut or defer and how to do so. Below are two examples of the effect of cognitive biases on downscoping decision-making.
The sunk cost effect
To investors, The fundamental limitations of downscoping
arise from the difficulty of managing the
decision-making processes used to
determine which objectives to cut
or defer and how to do sothe term sunk cost denotes costs already incurred and not recoverable. The sunk cost effect [Staw 1976] is a cognitive bias that tends to make us unwilling to terminate an effort. Our unwillingness arises largely from the difficulty of accepting failure, even when continuing the effort would only lead to greater losses. The sunk cost effect thus makes us unwilling to downscope our projects. We then continue to pursue unattainable objectives. But the sunk cost effect is even more insidious than that.
When we do decide to downscope, the sunk cost effect also compels us to make unwise choices of project elements to cut. Suppose a project is in trouble, and suppose we decide to downscope to address that trouble. The sunk cost effect can lead us to designate for cancellation those parts of the project in which we have the least invested. Instead, we would often do better to focus cuts on those parts of the project that are least justified in terms of business objectives.
At and above the scale of entire projects, portfolios, and programs, the situation is even more troubling. At these scales, downscoping amounts to project cancellation. The sunk cost effect causes us to prefer to cancel those projects in which we have invested least, all other things being equal, instead of cancelling the projects that have the least compelling business purpose. In this way, the sunk cost effect distorts business objectives when downscoping occurs under pressure.
Biased cost estimation
When we decide to abandon a project objective, there is a risk that the project elements so far constructed might include "anticipatory artifacts" whose sole purpose was support for the objective we've now decided to abandon. To the extent that the downscoping decision is based on budget or schedule considerations, we must consider the cost of two options. The "As-Is" option leaves these anticipatory artifacts largely in place, making adjustments only as necessary for supporting the surviving project objectives. The second option, "Cleaned-Up," removes all traces of anticipatory artifacts intended solely to support the soon-to-be-abandoned objectives.
For example, let's suppose that one of the objectives to be abandoned is an ability to support languages that use the Cyrillic alphabet, and that once this goal is removed, all supported languages will use only the Roman alphabet. In the As-Is option, the machinery for supporting multiple alphabets remains in place. The machinery is in place, but it is never invoked. We might even have a copy of the Cyrillic alphabet in the product. In the Cleaned-Up option, by contrast, we remove all evidence that we ever intended to support the Cyrillic alphabet.
But if we downscoped to save money and time, we must consider costs and schedule burdens associated with both options. To compare As-Is and Cleaned-Up we must estimate the costs of both. The two options differ, of course. As-Is has a higher future burden because of the technical debt associated with leaving in place the anticipatory artifacts that support the abandoned objective. Cleaned-Up has a higher immediate burden because of the costs and time associated with removing the anticipatory artifacts that support the abandoned objective.
Nearly all cases of downscoping that I'm aware of use a mix of both approaches — both As-Is and Cleaned-Up — but they clearly skew toward the As-Is option. One reason for the skew is the need to estimate As-Is and Cleaned-Up costs and schedules. And those estimates are subject to confirmation bias, which favors As-Is over Cleaned-Up. The result is that downscoping under pressure generally increases the burden of technical debt, which leaves the product with a higher maintenance cost profile for the indefinite future.
The role of project governance
Perhaps the most important factor limiting the effectiveness of downscoping under pressure is inadequate governance. Governance bodies that approve downscoped plans must ensure that the plans were devised using processes that mitigate the risk of decision distortion from political agendas and from cognitive biases such as the sunk cost effect and confirmation bias.
The urge to approve downscoping plans can be overpowering for everyone concerned. Governance teams are the last defense against unrealistic downscoping cost and schedule estimates. They would do a great service by requiring development of independent, "blind," estimates of cost and schedule for all options, including those rejected during the decision process.
Last words
These two posts have focused on the process of downscoping in project management. But the process is also used in other contexts. For example, one can view compromise in negotiation as a form of downscoping, in which the negotiation partners agree to limit their objectives as a technique for reaching mutual agreement. Much of the discussion in these two posts could carry over analogously in that context. Indeed, whenever we decide to alter the objectives of any kind of effort, especially under pressure, the observations contained in these two posts could prove applicable. First issue in this series Top Next Issue
Projects never go quite as planned. We expect that, but we don't expect disaster. How can we get better at spotting disaster when there's still time to prevent it? How to Spot a Troubled Project Before the Trouble Starts is filled with tips for executives, senior managers, managers of project managers, and sponsors of projects in project-oriented organizations. It helps readers learn the subtle cues that indicate that a project is at risk for wreckage in time to do something about it. It's an ebook, but it's about 15% larger than "Who Moved My Cheese?" Just . Order Now! .
Footnotes
Your comments are welcome
Would you like to see your comments posted here? rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Cognitive Biases at Work:
- The Stupidity Attribution Error
- In workplace debates, we sometimes conclude erroneously that only stupidity can explain why our debate
partners fail to grasp the elegance or importance of our arguments. There are many other possibilities.
- Motivated Reasoning and the Pseudocertainty Effect
- When we have a preconceived notion of what conclusion a decision process should produce, we sometimes
engage in "motivated reasoning" to ensure that we get the result we want. That's risky enough
as it is. But when we do this in relation to a chain of decisions in the context of uncertainty, trouble
looms.
- Seven Planning Pitfalls: II
- Plans are well known for working out differently from what we intended. Sometimes, the unintended outcome
is due to external factors over which the planning team has little control. Two examples are priming
effects and widely held but inapplicable beliefs.
- Seven More Planning Pitfalls: I
- Planners and members of planning teams are susceptible to patterns of thinking that lead to unworkable
plans. But planning teams also suffer vulnerabilities. Two of these are Group Polarization and Trips
to Abilene.
- Risk Acceptance: One Path
- When a project team decides to accept a risk, and when their project eventually experiences that risk,
a natural question arises: What were they thinking? Cognitive biases, other psychological phenomena,
and organizational dysfunction all can play roles.
See also Cognitive Biases at Work and Cognitive Biases at Work for more related articles.
Forthcoming issues of Point Lookout
- Coming January 22: Storming: Obstacle or Pathway?
- The Storming stage of Tuckman's model of small group development is widely misunderstood. Fighting the storms, denying they exist, or bypassing them doesn't work. Letting them blow themselves out in a somewhat-controlled manner is the path to Norming and Performing. Available here and by RSS on January 22.
- And on January 29: A Framework for Safe Storming
- The Storming stage of Tuckman's development sequence for small groups is when the group explores its frustrations and degrees of disagreement about both structure and task. Only by understanding these misalignments is reaching alignment possible. Here is a framework for this exploration. Available here and by RSS on January 29.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick
Recommend this issue to a friend
Send an email message to a friend
rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed