We began exploring bottlenecking patterns last time, focusing on the motivations of those who become bottlenecks. Certainly there are more motivations than we've mentioned so far, but let's turn now to explore measures that can reduce the incidence of the pattern, or, at least, reduce the consequences of bottlenecking when it does occur.
- Measure the incidence of bottlenecking
- Define metrics and gather data that measures the incidence of bottlenecking. Example metrics for individuals include: the percentage of their day spent in meetings; actual hours worked; email messages sent per week; email message response time; voice mail message age; text messages sent per week; and meetings rescheduled per week. One particularly interesting metric: the number of meetings to which they had to send a "substitute" because of a schedule conflct.
- Address bottlenecking in risk plans
- For projects in which bottlenecking is a significant risk, risk plans ought to address it. If monitoring bottlenecking metrics is part of risk planning, then risk plans can prescribe interventions when bottlenecking is indicated. For projects in which bottlenecking isn't regarded as a significant risk, risk plans should include evidence to that effect, and steps to be taken if events unfold differently.
- Remove temptations
- When people are assigned sets of responsibilities that span efforts that they once championed, and whose success was the foundation for their current stature, the temptation to hang on to their former roles can be irresistible indeed. Doing so contributes to their overload and therefore to bottlenecking. When expanding responsibilities of top performers, arranging to place their former responsibilities out of reach removes any such temptation.
- Monitor activities of political rivals
- Political rivals For projects in which bottlenecking
is a significant risk,
risk plans ought to address itof bottleneckers can be expected to be targeted for obscurity by the bottleneckers. That can happen because the responsibilities that are overloading the bottlenecker are often properly the responsibilities of the political rivals. Monitor the volume and the nature of the responsibilities political rivals have. If the workload of the rival is light, or the nature of the work is of lesser importance than the rival might be expected to have, the political agenda of the bottlenecker might be the cause. - Look to the supervisor
- Supervisors whose charges become bottlenecks do have some responsibility for the situation. Certainly supervisors cannot be fully aware of conditions from minute to minute, but supervisors can be held responsible for the problematic behavior people who have been bottlenecks for a month or more, or who are repeat offenders. And supervisors who have more than one subordinate who is a bottleneck are also problematic. The supervisor's supervisor must address these failures as performance issues for the supervisor.
Finally, does your organization reward martyrs — the people who work killing hours for months on end because only they know how to do whatever it is they do? Rewarding martyrs creates more martyrs. In the long run, martyrdom hurts the organization. First issue in this series Top Next Issue
Are your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!
Your comments are welcome
Would you like to see your comments posted here? rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Personal, Team, and Organizational Effectiveness:
- Dangerous Phrases
- I recently upgraded my email program to a new version that "monitors messages for offensive text."
It hasn't worked out well. But the whole affair got me to think about everyday phrases that do tend
to set people off. Here's a little catalog.
- Asking Clarifying Questions
- In a job interview, the interviewer asks you a question. You're unsure how to answer. You can blunder
ahead, or you can ask a clarifying question. What is a clarifying question, and when is it helpful to ask one?
- The Power and Hazards of Anecdotes: I
- Anecdotes are short stories — sometimes just a single sentence. They're powerful tools of persuasion,
but they can also be dangerous, to both anecdote tellers and anecdote listeners.
- Performance Mismanagement Systems: II
- One of the more counter-effective strategies incorporated into performance management systems is the
enterprise-wide uniform quota, known as a vitality curve. Its fundamental injustice breeds cynicism,
performance fraud, and toxic conflict. It produces performance assessments that are unrelated to enterprise
objectives.
- On Managing Life Event Risk
- Life events are those significant personal occurrences that lie outside the context of work. Some life
events cause enough stress and demand enough attention that they affect our performance at work. When
they do, they can affect our employers' plans.
See also Personal, Team, and Organizational Effectiveness and Personal, Team, and Organizational Effectiveness for more related articles.
Forthcoming issues of Point Lookout
- Coming January 22: Storming: Obstacle or Pathway?
- The Storming stage of Tuckman's model of small group development is widely misunderstood. Fighting the storms, denying they exist, or bypassing them doesn't work. Letting them blow themselves out in a somewhat-controlled manner is the path to Norming and Performing. Available here and by RSS on January 22.
- And on January 29: A Framework for Safe Storming
- The Storming stage of Tuckman's development sequence for small groups is when the group explores its frustrations and degrees of disagreement about both structure and task. Only by understanding these misalignments is reaching alignment possible. Here is a framework for this exploration. Available here and by RSS on January 29.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick
Recommend this issue to a friend
Send an email message to a friend
rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed