Point Lookout: a free weekly publication of Chaco Canyon Consulting
Volume 12, Issue 44;   October 31, 2012: Managing Non-Content Risks: I

Managing Non-Content Risks: I

by

When project teams and their sponsors manage risk, they usually focus on those risks most closely associated with the tasks — content risks. Meanwhile, other risks — non-content risks — get less attention. Among these are risks related to the processes and politics by which the organization gets things done.
Robert F. Scott and three of his party arrive at a tent left by Roald Amundsen near the South Pole

Robert F. Scott and three of his party arrive at a tent left by Roald Amundsen near the South Pole, on Thursday, January 18, 1912. Left to right are Capt. Scott, Capt. Oates, Dr. Wilson, and P.O. Evans. The photographer is Lt. Bowers. To many viewers, the party looks dejected, a hunch that is confirmed by Scott's journal entries. They had hoped to arrive first, and in that they failed. Scott's expedition suffered from several shortcomings, one of the more fundamental of which was a lack of focus. It was to be both a voyage of scientific discovery, and an attempt to be the first to reach the South Pole. Despite their failure to reach the Pole first, the party continued to pursue their scientific objectives. For instance, during the return from the Pole, the party continued to gather and carry rock samples. This activity was indeed unwise, because the effort involved in carrying the rocks was unsustainable, given their physical condition. When the bodies of Scott, Wilson and Bowers were found, their sledge was still encumbered with rock samples. By modern standards, if not contemporary standards, their return trip suffered from misplaced focus. The primary focus must always be preservation of life. By attempting to achieve both scientific and geographical goals, the expedition compromised both.

Risk management of efforts that lack focus or which have misplaced focus is difficult, if not impossible. Photo by Lt. Henry "Birdie" Bowers, British Antarctic Expedition, 1910-13.

When we undertake tasks in organizations, we face risks. The most obvious risks are those that are most closely related to the task at hand. These risks, which we might call content risks include factors such as technological unknowns, resource availability, and competition. But there are other risks, often overlooked, that can dramatically influence our chances for success.

One of these is risk management risk, which is the risk that the risk management process is flawed, due to such factors as organizational political correctness, organizational blind spots, or the risk that political phenomena render certain risks invisible to risk managers.

Here are some examples of non-content risks, with suggestions for managing them. In this Part I, we emphasize risk sources related to perceptions.

Misplaced or excessive focus
Typically, organizations have in place processes that maintain focus on what they do well. For example, approvals are required to allocate resources to forward-looking initiatives. But some organizations are excessively zealous about maintaining focus, and some are mistaken about where that focus should be. For instance, organizations that need to undertake efforts to adopt new technologies to serve their existing customers sometimes refrain from doing so because of advocacy by those representing customers most resistant to change.
Advocates of advanced initiatives would do well to protect their activities from notice until their relevance is evident to all, easily explained, and easily defended. Working demonstrations are especially useful.
Resentment bred by success
We rarely consider risks associated with success. But here's one: your effort is so successful and appealing that people seek to join your team. Having to decline these offers because of insufficient resources isn't much of a problem, because people do understand that issue. The more difficult problem is the resentment such success can engender on the part of potential political adversaries.
When appropriate,Advocates of advanced initiatives
would do well to protect their
activities from notice until their
relevance is evident to all
devise plans for dealing with such challenges. One helpful guideline: don't publicize your success internally unless the publicity materially aids the effort and you have political strength sufficient to withstand challenges.
Unsustainable loads
The term "unsustainable load" usually evokes thoughts of overload and burnout. Certainly, high loads are unsustainable. But low loads can also be unsustainable. Sustainability of a given workload is in part determined by perceived differences between one's own workload and the workloads of colleagues and peers.
Loads much higher, or much lower, than cultural norms are unsustainable in the long term. High loads cause burnout and bailout; low loads attract those with agendas other than your own, and risk losing people (and stakeholders) from boredom and idleness. Strive for workloads near but slightly above the cultural norm.

Next time, we'll turn our attention to risks arising from organizational politics.  Managing Non-Content Risks: II Next issue in this series  Go to top Top  Next issue: Managing Non-Content Risks: II  Next Issue

303 Secrets of Workplace PoliticsIs every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info

Your comments are welcome

Would you like to see your comments posted here? rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

The Leonard P. Zakim Bunker Hill BridgeThe Cheapest Way to Run a Project Is with Enough Resources
Cost reduction is so common that nearly every project plan today should include budget and schedule for several rounds of reductions. Whenever we cut costs, we risk cutting too much, so it pays to ask, "If we do cut too much, what are the consequences?"
FootprintsStatus Risk and Risk Status
One often-neglected project risk is the risk of inaccurately reported status. That shouldn't be surprising, because we often fail to report the status of the project's risks, as well. What can we do to better manage status risk and risk status?
My right foot. Arrow indicates the location of the break.My Right Foot
There's nothing like an injury or illness to teach you some life lessons. Here are some things I learned recently when I temporarily lost some of my independence.
Statue of Hermes with modern headTeamwork Myths: Formation
Much of the conventional wisdom about teams is in the form of over-generalized rules of thumb, or myths. In this first part of our survey of teamwork myths, we examine two myths about forming teams.
Big Spring, a giant karst spring in The Ozarks, MissouriDefect Streams and Their Sources
Regarding defects as elements of a stream provides a perspective that aids in identifying causes other than negligence. Examples of root causes are unfunded mandates, misallocation of the cost of procedure competence, and frequent changes in procedures.

See also Project Management and Project Management for more related articles.

Forthcoming issues of Point Lookout

A game of Jenga underwayComing September 4: Beating the Layoffs: I
If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily before the layoffs can carry significant advantages. Here are some that relate to self-esteem, financial anxiety, and future employment. Available here and by RSS on September 4.
A child at a fork in a pathAnd on September 11: Beating the Layoffs: II
If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily can carry advantages. Here are some advantages that relate to collegial relationships, future interviews, health, and severance packages. Available here and by RSS on September 11.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at X, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.