Point Lookout: a free weekly publication of Chaco Canyon Consulting
Volume 10, Issue 11;   March 17, 2010: Risk Management Risk: I

Risk Management Risk: I

by

Risk Management Risk is the risk that a particular risk management plan is deficient. It's often overlooked, and therefore often unmitigated. We can reduce this risk by applying some simple procedures.
Example of an unsecured driver-side floor mat trapping the accelerator pedal in a 2007 Toyota Lexus ES350

Example of an unsecured driver-side floor mat trapping the accelerator pedal in a 2007 Toyota Lexus ES350. We don't yet know much about the root cause of quality problems in recent models of vehicles designed and manufactured by Toyota, but we can already evaluate the company's public response to the reports of problems. Briefly, their response has been erratic. In part, this might be due to the company's inexperience with defects. Their record has been so good, and recalls so few, that they might have had an organizational blind spot relating to the risk of public exposure of defects in their products. Undoubtedly, this blind spot is now being corrected, albeit in a manner most unpleasant for all concerned. Photo courtesy U.S. National Highway Traffic Safety Administration.

Risk plans are rarely perfect. For complex projects, unanticipated risk will almost certainly materialize. We can deal with this risk — I'll call it risk management risk — if we adopt some simple practices. Let's begin with some examples of organizational and political risks.

Organizational blind spots
Organizational risk management asset bases usually consist of previously developed risk plans and risk plan elements, documented risk plan development procedures, and personal experiences.
Although referring to these assets might uncover risks that any particular risk manager might not otherwise consider, relying on the asset base probably won't uncover risks not included there. Since continuous organizational change almost certainly exposes the organization to risks never before seen, these asset bases have blind spots.
To limit these blind spots, analyze the results of retrospectives to determine what risks were unanticipated. They provide clues to the location of the organization's blind spots.
Organizational political correctness
In general discourse, political correctness requires that we shape our statements and behavior — if not our opinions — to conform to a generally accepted ideological standard. Organizational political correctness provides an analogous constraint relative to the ideology and views of the organization.
Organizational Organizational political correctness
can limit the ability of risk managers
to address significant risks
political correctness can limit the ability of risk managers to address significant risks, when even discussing such risks calls into question organizational beliefs, or the beliefs of those who have internal political power.
If a common theme appears among unanticipated risks, if those risks are evident to many, and if the same risks materialize across many projects, organizational political correctness could be a cause. Organizational culture change is required to address this risk.
Political risk
The organizational value of any project is determined, in part, by the political clout of its advocates. How an organization values a project can present risks to it through resource allocation, schedule, and budget.
Although these risks are widely understood, talking about them openly and planning for them in writing is often difficult, for reasons far beyond organizational political correctness. For the politically weak project, committing to writing and review any plan to deal with political risks simply provides a roadmap to rival projects if they are politically stronger. Such a risk plan is often effectively countered before it can be implemented. In some cases, it might even be forbidden. This effect is especially pronounced if a state of toxic conflict persists between the departments, leaders, or champions of the two projects.
Two factors suggest the presence of political risk. First is the absence of any explicit mention of political risk from the risk plans of politically weak projects. A second indicator can be changes in the execution plan of politically stronger projects, especially following publication of the risk plan of a politically weaker project.

In Part II, we'll examine risk dynamics and risk interactions.  Risk Management Risk: II Next issue in this series  Go to top Top  Next issue: Risk Management Risk: II  Next Issue

303 Secrets of Workplace PoliticsIs every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info

Your comments are welcome

Would you like to see your comments posted here? rbrenfHlRlTgqCIXkUHBTner@ChacrEuHRQPYVKkOucGfoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

US Space Shuttle LaunchSome Causes of Scope Creep
When we suddenly realize that our project's scope has expanded far beyond its initial boundaries — when we have that how-did-we-ever-get-here feeling — we're experiencing the downside of scope creep. Preventing scope creep starts with understanding how it happens.
Ice on Challenger's launch pad hours before the launchDesign Errors and Groupthink
Design errors cause losses, lost opportunities, accidents, and injuries. Not all design errors are one-offs, because their causes can be fundamental. Here's a first installment of an exploration of some fundamental causes of design errors.
Ammi Visnaga, a nile weed that has medicinal valueDown in the Weeds: II
To be "down in the weeds," in one of its senses, is to be lost in discussion at a level of detail inappropriate to the current situation. Here's Part II of our exploration of methods for dealing with this frustrating pattern so common in group discussions.
Astronauts Musgrave and Hoffman install corrective optics during the Hubble Telescope's Service Mission 1How We Waste Time: I
Time is the one workplace resource that's evenly distributed. Everyone gets exactly the same share, but some use it more wisely than others. Here's Part I of a little catalog of ways we waste time.
A reversed calendar pageSome Perils of Reverse Scheduling
Especially when time is tight, project sponsors sometimes ask their project managers to produce "reverse schedules." They want to know what would have to be done by when to complete their projects "on time." It's a risky process that produces aggressive schedules.

See also Project Management and Project Management for more related articles.

Forthcoming issues of Point Lookout

Someone got the wrong information about which sneakers to wear on which feetComing April 30: On Planning in Plan-Hostile Environments: II
When we finally execute plans, we encounter obstacles. So we find workarounds or adjust the plans. But there are times when nothing we try gets us back on track. When this happens for nearly every plan, we might be working in a plan-hostile environment. Available here and by RSS on April 30.
A dramatization of a mobbing incidentAnd on May 7: Subject Matter Bullying
Most workplace bullying tactics have analogs in the schoolyard — isolation, physical attacks, name-calling, and rumor-mongering are common examples. Subject matter bullying might be an exception, because it requires expertise in a sophisticated knowledge domain. And that's where trouble begins. Available here and by RSS on May 7.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenfHlRlTgqCIXkUHBTner@ChacrEuHRQPYVKkOucGfoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at Bluesky, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.