Volume 5, Issue 48;   November 30, 2005: Nine Project Management Fallacies: I

Nine Project Management Fallacies: I

by

Most of what we know about managing projects is useful and effective, but some of what we "know" just isn't so. Identifying the fallacies of project management reduces risk and enhances your ability to complete projects successfully.

Nan pushed the door open, and she and Trish stepped out of the conference center into the morning air. On their first break from the off-site meeting, they hadn't quite yet relaxed from the pressure cooker that was the final stretch of Marigold, their latest project. It hadn't gone well, and they were all spending three days trying to figure out what happened.

Two colleagues chatting on their morning break"So what do you think?" Nan opened.

"I've been to off-sites before," said Trish. "But this is the first time I've felt hopeful that truth would come out."

Nan agreed. "Me too. I liked the bit about myths and fallacies."

Nan sat down on one of the plastic chairs. Trish sat too. "But knowing these fallacies," she asked, "won't we just get better at fooling ourselves? If we could get any better which I seriously doubt."

Nan smiled. "Well, I think his point was that by naming the fallacies, it gets harder to use them."

And Nan is right about that. By naming the fallacies, the patterns become obvious to everyone, which deters us from using them. Here's Part I of a little catalog of the fallacies of project management. For Part II, see "Nine Project Management Fallacies: II," Point Lookout for December 14, 2005.

Universal awareness
of common fallacies
deters us all
from using them
The Fallacy of Positivism
The Fallacy of Positivism holds that if we believe we can accomplish something, we're more likely to actually accomplish it; and inversely, if we express doubts about accomplishing something, we're less likely to execute it successfully.
This fallacy is especially tempting to leaders who want to motivate reluctant teams to attempt (or keep trying to do) the impossible. They're using it as a tool of manipulation.
All things being equal, it's probably helpful to have a positive attitude. But Truth is most important. Be positive when it's appropriate, and express doubts when they're real and relevant. Both staying positive and expressing doubt inappropriately can lead to catastrophe.
The Bad Actor Fallacy
If a team exhibits a repeated pattern of dysfunction, we commit the Bad Actor Fallacy when we assume that one single team member is the likely cause of the problem.
Isolating the cause of a team problem to a single individual is tempting because it suggests that dealing with that individual can resolve the problem. No need for messy and expensive team interventions; no need for involving more than one person.
While it's possible for a single individual to keep a team in a state of dysfunction, more typically many individuals contribute to team problems. Team performance is an attribute of the team's system, and the organization in which that team is embedded.

One more fallacy is perhaps most common: the Purity Fallacy, which holds that we are personally pure: we never use fallacies ourselves. We all use them, of course — we're human. The trick is to catch yourself when you do.  Nine Project Management Fallacies: II Next issue in this series  Go to top Top  Next issue: Comfortable Ignorance  Next Issue

52 Tips for Leaders of Project-Oriented OrganizationsAre your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!

Your comments are welcome

Would you like to see your comments posted here? rbrenfHlRlTgqCIXkUHBTner@ChacrEuHRQPYVKkOucGfoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

The Leonard P. Zakim Bunker Hill BridgeThe Cheapest Way to Run a Project Is with Enough Resources
Cost reduction is so common that nearly every project plan today should include budget and schedule for several rounds of reductions. Whenever we cut costs, we risk cutting too much, so it pays to ask, "If we do cut too much, what are the consequences?"
The interior of an Apple store, location unknownPersonnel-Sensitive Risks: I
Some risks and the plans for managing them are personnel-sensitive in the sense that disclosure can harm the enterprise or its people. Since most risk management plans are available to a broad internal audience, personnel-sensitive risks cannot be managed in the customary way. Why not?
Three simple carabinersTeam Risks
Working in teams is necessary in most modern collaborations, but teamwork does carry risks. Here are some risks worth mitigating.
Panama Canal constructionAvoid Having to Reframe Failure
Yet again, we missed our goal — we were late, we were over budget, or we lost to the competition. But how can we get something good out of it?
Astronauts Musgrave and Hoffman install corrective optics during the Hubble Telescope's Service Mission 1How We Waste Time: I
Time is the one workplace resource that's evenly distributed. Everyone gets exactly the same share, but some use it more wisely than others. Here's Part I of a little catalog of ways we waste time.

See also Project Management and Project Management for more related articles.

Forthcoming issues of Point Lookout

Someone got the wrong information about which sneakers to wear on which feetComing April 30: On Planning in Plan-Hostile Environments: II
When we finally execute plans, we encounter obstacles. So we find workarounds or adjust the plans. But there are times when nothing we try gets us back on track. When this happens for nearly every plan, we might be working in a plan-hostile environment. Available here and by RSS on April 30.
A dramatization of a mobbing incidentAnd on May 7: Subject Matter Bullying
Most workplace bullying tactics have analogs in the schoolyard — isolation, physical attacks, name-calling, and rumor-mongering are common examples. Subject matter bullying might be an exception, because it requires expertise in a sophisticated knowledge domain. And that's where trouble begins. Available here and by RSS on May 7.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenfHlRlTgqCIXkUHBTner@ChacrEuHRQPYVKkOucGfoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at Bluesky, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
101 Tips for Managing ConflictFed up with tense, explosive meetings? Are you the target of a bully? Learn how to make peace with conflict.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.