Volume 1, Issue 12;   March 21, 2001: The Cheapest Way to Run a Project Is with Enough Resources

The Cheapest Way to Run a Project Is with Enough Resources

by

Cost reduction is so common that nearly every project plan today should include budget and schedule for several rounds of reductions. Whenever we cut costs, we risk cutting too much, so it pays to ask, "If we do cut too much, what are the consequences?"

BBoston's Big Dig, the largest highway project in U.S. history, was originally projected to cost about $2 billion. The price now is over $14 billion. I don't know why they're over budget, but I do know that there has been intense pressure to hold costs down. Maybe part of their problem is the pressure to reduce costs.

The Leonard P. Zakim Bunker Hill Bridge

The Leonard P. Zakim Bunker Hill Bridge, part of Boston's Big Dig, while it was still under construction. Defects directly traceable to budget cuts led to numerous problems in the project's tunnels, and probably are tied to the death of one tunnel user. Photo courtesy the Big Dig.

Since the need to cut costs suggests that earlier estimates were off, why do we believe the new estimates? They're usually made under extreme time pressure, and with obvious bias. They might even be worse than the estimates they replace.

Yet, we do it and we do it again. Whenever we cut budgets, we risk cutting too much. And then we must deal with a hard truth: if we cut too much, the project will likely cost even more than if we hadn't cut at all.

When we cut too much, new mechanisms — many invisible — kick in, and all are beyond the control of project management. Uncontrolled processes lead to uncontrolled costs, and that's why cutting too much raises costs. Some examples:

Wishing
Responding to the call for cuts, people re-estimate their work, knowing that only the "right answers" can save their pieces of the project. Unaware, they bias their estimates. Overruns are inevitable.
Bootlegging
When we charge time to one project and work on another, or when we "borrow" equipment, we're bootlegging. It's widespread, and it's completely off the books.
Hoarding
Excessive budget
cuts encourage
"underground" behavior,
which is hard
to control
If we believe that we won't gain approval for additional staff, we might be tempted to keep some people we have, even when we don't really need them, because we doubt that we can get them back when we do need them again. So when money is tight, we find some people sitting around.
Bingeing and purging
When an organization goes through a sequence of "freezes," it inevitably goes through a matching sequence of thaws. During thaws we grab whatever we can. Often, this grab goes beyond satisfying backlogged needs, and becomes a true binge. Like squirrels burying acorns, we acquire what we can whether we need it or not.
Deferring
When budgets are tight, we sometimes defer addressing problems. For example, if a project is late, we shorten testing. This defers discovery of problems, often until after the product ships, when resolving the problems is even more expensive. The project cost is reduced, but the cost to the enterprise climbs dramatically.

Find out if any of this stuff is happening in your organization. If it's increasing, perhaps you're trying to run projects with budgets that are too small. Go to top Top  Next issue: The Slippery Slope That Isn't  Next Issue

How to Spot a Troubled Project Before the Trouble StartsProjects never go quite as planned. We expect that, but we don't expect disaster. How can we get better at spotting disaster when there's still time to prevent it? How to Spot a Troubled Project Before the Trouble Starts is filled with tips for executives, senior managers, managers of project managers, and sponsors of projects in project-oriented organizations. It helps readers learn the subtle cues that indicate that a project is at risk for wreckage in time to do something about it. It's an ebook, but it's about 15% larger than "Who Moved My Cheese?" Just . Order Now! .

One symptom of resource starvation is the urge to make every effort "count" towards the ultimate deliverable. For a discussion of the downside of this approach, see "Trying to Do It Right the First Time Isn't Always Best," Point Lookout for March 14, 2007.

Your comments are welcome

Would you like to see your comments posted here? rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Stuffed bearsStart a Project Nursery
In a Project Nursery, professionals from across the entire organization collaborate to conceive of new projects. When all organizational elements help decide which projects to investigate, the menu they develop best suits organizational needs and capabilities.
Gen. T.J. "Stonewall" JacksonFlanking Maneuvers
Historically, military logistics practice has provided a steady stream of innovations to many fields, including project management. But project managers can learn even more if we investigate battlefield tactics.
The U.S. Capitol at nightNepotism, Patronage, Vendettas, and Workplace Espionage
Normally, you terminate or reassign team members who actually inhibit progress. Here are some helpful insights and tactics to use when termination or reassignment is impossible.
A model of a space station proposed in 1952 by Wernher von BraunHigher-Velocity Problem Definition
Typical approaches to shortening time-to-market for new products often involve accelerating problem solving. Accelerating problem definition can also help, but a curious paradox stands in the way.
The S.S. Eastland, in Cleveland, Ohio, around 1911On Anticipating Consequences
Much of what goes wrong when we change systems to improve them falls into a category we call unanticipated consequences. Even when we lack models that can project these results accurately, morphological analysis can help us avoid much misery.

See also Project Management and Project Management for more related articles.

Forthcoming issues of Point Lookout

A game of Jenga underwayComing September 4: Beating the Layoffs: I
If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily before the layoffs can carry significant advantages. Here are some that relate to self-esteem, financial anxiety, and future employment. Available here and by RSS on September 4.
A child at a fork in a pathAnd on September 11: Beating the Layoffs: II
If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily can carry advantages. Here are some advantages that relate to collegial relationships, future interviews, health, and severance packages. Available here and by RSS on September 11.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at X, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
101 Tips for Managing ConflictFed up with tense, explosive meetings? Are you the target of a bully? Learn how to make peace with conflict.
Reader Comments About My Newsletter
A sampling:
  • Your stuff is brilliant! Thank you!
  • You and Scott Adams both secretly work here, right?
  • I really enjoy my weekly newsletters. I appreciate the quick read.
  • A sort of Dr. Phil for Management!
  • …extremely accurate, inspiring and applicable to day-to-day … invaluable.
  • More
52 Tips for Leaders of Project-Oriented OrganizationsAre your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around.
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.
Comprehensive collection of all e-books and e-bookletsSave a bundle and even more important save time! Order the Combo Package and download all ebooks and tips books at once.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!