Volume 19, Issue 38;   September 18, 2019: The Planning Fallacy and Self-Interest

The Planning Fallacy and Self-Interest

by

A well-known cognitive bias, the planning fallacy, accounts for many unrealistic estimates of project cost and schedule. Overruns are common. But another cognitive bias, and organizational politics, combine with the planning fallacy to make a bad situation even worse.
An unfinished building, known as Szkieletor

An unfinished building, known as Szkieletor. Construction began in 1975, but stopped permanently in 1981 because of economic constraints and political unrest. Sometimes budgets aren't overrun. Sometimes they just run out. Image (cc) pl:Wikipedysta:Macieias courtesy Wikipedia.

Project plans usually include estimates of costs and schedules in addition to plans for work to be done, and the order of doing that work. Sometimes we fail to complete all the work we had in mind; sometimes we find we cannot do some work we wanted to do; sometimes we discover additional work we needed to do. But overall, the work actually done in a project does roughly approximate the work that was planned. Not so for cost and schedule. Cost and schedule can differ from projections by double, triple, and more, even when we make allowances for differences between work planned and work actually done.

In a 1977 report, Daniel Kahneman and Amos Tversky identify a particular cognitive bias, the planning fallacy, which afflicts planners. [Kahneman 1977] [Kahneman 1979] They discuss two types of information used by planners. Singular information is specific to the project at hand; distributional information is drawn from similar past efforts. The planning fallacy is the tendency of planners to pay too little attention to distributional information and too much attention to singular information, even when the singular information is scanty or questionable. Planners tend to underestimate cost and schedule by failing to harvest lessons from the distributional information, which is inherently more diverse and reliable than singular information.

But even when planners attend to distributional information, two forms of self-serving considerations can lead planners to make estimates that cannot be met. Here's how.

Self-serving bias
Choosing local experts is a common pattern for designating people to make estimates of cost and schedule. Usually the experts designated tend to be people who've done similar work in the past, and sometimes they must assess their own past work. When estimators must evaluate their own work, they have a conflict of interest that can compromise objectivity as a result of a cognitive bias known as self-serving bias. [Campbell 1999] Self-serving bias causes us to perceive ourselves more positively than objective judgment warrants. We tend to attribute successes to our own talents and decisions, and attribute failures to external factors.
When the The work actually done in a
project does roughly approximate
the work that was planned.
Not so for cost and schedule.
estimators designated for a project were themselves involved in the past efforts they're evaluating for estimation purposes — what Kahneman and Tversky call distributional information — self-serving bias tends to lead them to biased conclusions, which they then use to make projections for the project whose cost and schedule they're estimating.
Organizational politics
From the perspective of objective estimation based on balanced assessment of distributional and singular information, organizational politics can make a bad situation even worse. Estimators who are evaluating past efforts in which they played roles can use their evaluations as tools of what psychologists call impression management — to make themselves look good. They can thus enhance their own prospects for advancement. [Drory 2006] In this way, politics can limit the willingness of estimators to faithfully represent sources of successes and failures in past efforts. In effect, to gain political advantage, estimators tend to attribute too much of the reason for past successes to their own actions, and too much of the reason for past failures to external factors or to the actions of others, especially political rivals.

The distortions that result from the planning fallacy, from self-serving bias, and from organizational politics can reduce the chances that estimators will produce reliable results. When that happens, cost overruns and schedule delays become more likely. Go to top Top  Next issue: Planning Disappointments  Next Issue

303 Secrets of Workplace PoliticsIs every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics, filled with tips and techniques for succeeding in workplace politics. More info

Footnotes

Comprehensive list of all citations from all editions of Point Lookout
[Kahneman 1977]
Daniel Kahneman and Amos Tversky. "Intuitive Prediction: Biases and Corrective Procedures," Technical Report PTR-1042-7746, Defense Advanced Research Projects Agency, June 1977. Available here. Retrieved 19 September 2017. Back
[Kahneman 1979]
Daniel Kahneman and Amos Tversky. "Intuitive Prediction: Biases and Corrective Procedures," Management Science 12 (1979), 313-327. Back
[Campbell 1999]
W. Keith Campbell and Constantine Sedikides. "Self-threat magnifies the self-serving bias: A meta-analytic integration," Review of General Psychology 3:1 (1999), 23-43. Available here. Retrieved 2 September 2019. Back
[Drory 2006]
Amos Drory and Nurit Zaidman. "The politics of impression management in organizations: contextual effects," in Handbook of Organizational Politics, Eran Vigoda-Gadot and Amos Drory, eds., Cheltenham, UK and Northampton, MA, USA: Edward Elgar (2006), 75-85. Back

Your comments are welcome

Would you like to see your comments posted here? rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

Icelandic currentsRestarting Projects
When a project gets off track, we sometimes cancel it. But since canceling projects takes a lot of courage, we look for ways to save them if we can. Often, things do turn out OK, and at other times they don't. There's a third choice, between pressing on with a project and canceling it. We can restart.
Rough-toothed dolphinThe Injured Teammate: I
You're a team lead, and one of the team members is very ill or has been severely injured. How do you handle it? How do you break the news? What does the team need? What do you need?
Ice on Challenger's launch pad hours before the launchDesign Errors and Groupthink
Design errors cause losses, lost opportunities, accidents, and injuries. Not all design errors are one-offs, because their causes can be fundamental. Here's a first installment of an exploration of some fundamental causes of design errors.
Selling an ideaRisk Creep: II
When risk events occur, and they're of a kind we never considered before, it's possible that we've somehow invited those risks without realizing we have. This is one way for risk to creep into our efforts. Here's Part II of an exploration of risk creep.
Children playing a computer gameThe Risk of Astonishing Success
When we experience success, we're more likely to develop overconfidence. And when the success is so extreme as to induce astonishment, we become even more vulnerable to overconfidence. It's a real risk of success that must be managed.

See also Project Management and Project Management for more related articles.

Forthcoming issues of Point Lookout

A diagram of the cross section of a boat with a single water ballast tank at the bottomComing January 22: Storming: Obstacle or Pathway?
The Storming stage of Tuckman's model of small group development is widely misunderstood. Fighting the storms, denying they exist, or bypassing them doesn't work. Letting them blow themselves out in a somewhat-controlled manner is the path to Norming and Performing. Available here and by RSS on January 22.
The Eisenhower Matrix of Urgency by ImportanceAnd on January 29: A Framework for Safe Storming
The Storming stage of Tuckman's development sequence for small groups is when the group explores its frustrations and degrees of disagreement about both structure and task. Only by understanding these misalignments is reaching alignment possible. Here is a framework for this exploration. Available here and by RSS on January 29.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenjTnUayrCbSnnEcYfner@ChacdcYpBKAaMJgMalFXoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at X, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
Go For It: Sometimes It's Easier If You RunBad boss, long commute, troubling ethical questions, hateful colleague? Learn what we can do when we love the work but not the job.
303 Tips for Virtual and Global TeamsLearn how to make your virtual global team sing.
101 Tips for Managing ChangeAre you managing a change effort that faces rampant cynicism, passive non-cooperation, or maybe even outright revolt?
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Exchange your "personal trade secrets" — the tips, tricks and techniques that make you an ace — with other aces, anonymously. Visit the Library of Personal Trade Secrets.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.