Language and terminology are the tools we use to express our thoughts. But language and terminology can do much more — they can actually influence the way we think. And that influence isn't always helpful.
Consider risk. In project management, and fields closely related, there's an ongoing conversation about differences between the term risk and the term issue. Although disagreement and confusion persist, most people agree about two points. First, a risk is an event or condition that might or might not occur, while an issue is an event or condition that has already occurred, or which will certainly occur. Second, both risks (if they occur) and issues have adverse consequences for objectives.
The principal difference between risks and issues is that risks have probability less than 100%; issues have probability 100%.
This distinction leaves at least one situation uncovered: what do we call adverse events that have occurred (or which certainly will occur), but which as yet have escaped notice? I call them undetected issues. Undetected issues can be problematic, because although we treat them as risks, they aren't risks at all.
How does all this relate to our use of language? When we think of undetected issues as risks, we tend to regard them as not yet having happened, as opposed to having happened and not yet having been detected. Thinking about them this way can be problematic. For example, thinking of a condition as not yet having happened can lead to dismissing as pointless — or not worthwhile — any plan to determine whether or not it has already occurred. Why search for something that hasn't happened?
On the other hand, we might be more willing to expend resources to uncover the presence of undetected issues. When we do search, we're more likely to find them.
For example, consider the mission of Apollo XIII. A liquid oxygen tank exploded during Hour 55 of the mission due to When we think of undetected issues
as risks, we tend to regard them
as not yet having happened, as
opposed to having happened
and not yet having been detecteddamaged insulation on wires inside the tank, which resulted from procedures executed years earlier. Before installation in the vehicle, the damage was a risk. After installation, it was not a risk at all — it was an undetected issue. And post-incident, a thorough investigation did uncover the undetected issue. How would the mission have been affected if NASA — before launch — had conducted a more thorough search for undetected issues?
Many project teams now develop risk management plans. Few of these plans address the risk of undetected issues. If we think clearly about the distinctions among issues, risks, undetected issues, and the risk of undetected issues, we're more likely to include mechanisms in the design of our systems — and procedures, schedule, and resources in the design of our projects — that facilitate detecting as-yet-undetected issues.
We'll explore some practices that can help teams uncover undetected issues next time. Next issue in this series Top Next Issue
Are your projects always (or almost always) late and over budget? Are your project teams plagued by turnover, burnout, and high defect rates? Turn your culture around. Read 52 Tips for Leaders of Project-Oriented Organizations, filled with tips and techniques for organizational leaders. Order Now!
Your comments are welcome
Would you like to see your comments posted here? rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Project Management:
- The Injured Teammate: I
- You're a team lead, and one of the team members is very ill or has been severely injured. How do you
handle it? How do you break the news? What does the team need? What do you need?
- Ground Level Sources of Scope Creep
- We usually think of scope creep as having been induced by managerial decisions. And most often, it probably
is. But most project team members — and others as well — can contribute to the problem.
- Missing the Obvious: II
- With hindsight, we sometimes recognize that we could have predicted the very thing that just now surprised
us. Somehow, we missed the obvious. Why does this happen?
- Some Risks of Short-Term Fixes
- When we encounter a problem at work, we must choose between short-term fixes (also known as workarounds)
and long-term solutions. Often we choose workarounds without appreciating the risks we're accepting
— until too late.
- Higher-Velocity Problem Definition
- Typical approaches to shortening time-to-market for new products often involve accelerating problem
solving. Accelerating problem definition can also help, but a curious paradox stands in the way.
See also Project Management and Project Management for more related articles.
Forthcoming issues of Point Lookout
- Coming September 4: Beating the Layoffs: I
- If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily before the layoffs can carry significant advantages. Here are some that relate to self-esteem, financial anxiety, and future employment. Available here and by RSS on September 4.
- And on September 11: Beating the Layoffs: II
- If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily can carry advantages. Here are some advantages that relate to collegial relationships, future interviews, health, and severance packages. Available here and by RSS on September 11.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick
Recommend this issue to a friend
Send an email message to a friend
rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed