We've already examined the fundamentals of improvisation, and improvisation as a group process. We now examine its impact on risk management. Because improvisation will almost certainly be necessary in most projects, we ought to anticipate it by allocating budget, schedule, and management time to address improvisations. Here are some suggestions for adjusting risk plans once improvisation becomes necessary.
- Directed improvisation is risky
- Sometimes decision makers demand improvisation. Directed improvisation entails unique risks, because the director might not be very familiar with the project, its technology, or its staff. When improvisation is directed, defer as much as possible, until the consequences of the directed improvisation become clear.
- Improvising without content-related cause is risky
- Some improvising happens even when the project plan seems to be working well. On these occasions, the drivers of the decision to improvise are unrelated to the project work itself, and often are related to the use of the deliverables. For instance, the decision maker might seek delivery during a fiscal window earlier than planned. The more sudden the decision is, the riskier it is.
- The need to improvise could be a signal
- Even though projects are inherently difficult to plan, a real need to improvise can result from a poor plan — or no plan. If a truly thoughtful plan does exist, the need to improvise signals nothing more than the inherent difficulties of project management. But if the project plan was developed in haste, perhaps by cloning plans for supposedly similar work, further trouble probably lies ahead.
- Improvisations can create timing risks
- If improvisation is necessary, the project schedule is probably changed or even disrupted. Usually, task schedules slip to later dates. Examine the new schedule to determine whether necessary resources are still available. This is especially tricky when resources are shared with other projects.
- Improvisations tend to transfer risk
- Any work undertaken during improvisation could potentially require resources that were allocated to something else, including other projects. The effects of improvisation can therefore The effects of improvisation
can ripple widely
through the organizationripple widely through the organization. Improvisations in one project kick off improvisations elsewhere, which can sometimes export risk as well. Be alert to improvisations wherever they occur, and address them in your risk plan. - Improvisations enhance creativity risk
- Improvisation requires — and stimulates — creativity. In the project context, a successful improvisation can bring to light new approaches to work already completed, planned, or underway. Sometimes this new thinking is helpful or even necessary, and should be applied. And sometimes it isn't really essential. Apply new ideas where necessary, and manage creativity risk — the temptation to use good ideas to improve what is already good enough.
Whatever the reason for improvisation, an often-neglected set of consequences lies hidden in the project's risk plan. Record carefully the improvised actions undertaken, and when normal activity resumes, immediately revisit the risk plan. If you don't, you might be improvising again before you know it. First issue in this series Top Next Issue
Projects never go quite as planned. We expect that, but we don't expect disaster. How can we get better at spotting disaster when there's still time to prevent it? How to Spot a Troubled Project Before the Trouble Starts is filled with tips for executives, senior managers, managers of project managers, and sponsors of projects in project-oriented organizations. It helps readers learn the subtle cues that indicate that a project is at risk for wreckage in time to do something about it. It's an ebook, but it's about 15% larger than "Who Moved My Cheese?" Just . Order Now! .
Your comments are welcome
Would you like to see your comments posted here? rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend me your comments by email, or by Web form.About Point Lookout
Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.
This article in its entirety was written by a human being. No machine intelligence was involved in any way.
Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.
Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.
Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.
Related articles
More articles on Project Management:
- Guidelines for Sharing "Resources"
- Often, team members belong to several different teams. The leaders of teams whose members have divided
responsibilities must sometimes contend with each other for the efforts and energies of the people they
share. Here are some suggestions for sharing people effectively.
- Scope Creep and the Planning Fallacy
- Much is known about scope creep, but it nevertheless occurs with such alarming frequency that in some
organizations, it's a certainty. Perhaps what keeps us from controlling it better is that its causes
can't be addressed with management methodology. Its causes might be, in part, psychological.
- Wishful Interpretation: II
- Wishful "thinking," as we call it, can arise in different ways. One source is the pattern
of choices we make when we interpret what we see, what we hear, or any other information we receive.
Here's Part II of an inventory of ways our preferences and wishes affect how we interpret the world.
- Risk Creep: I
- Risk creep is a term that describes the insidious and unrecognized increase in risk that occurs despite
our every effort to mitigate risk or avoid it altogether. What are the dominant sources of risk creep?
- Power Distance and Teams
- One of the attributes of team cultures is something called power distance, which is a measure
of the overall comfort people have with inequality in the distribution of power. Power distance can
determine how well a team performs when executing high-risk projects.
See also Project Management and Project Management for more related articles.
Forthcoming issues of Point Lookout
- Coming September 4: Beating the Layoffs: I
- If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily before the layoffs can carry significant advantages. Here are some that relate to self-esteem, financial anxiety, and future employment. Available here and by RSS on September 4.
- And on September 11: Beating the Layoffs: II
- If you work in an organization likely to conduct layoffs soon, keep in mind that exiting voluntarily can carry advantages. Here are some advantages that relate to collegial relationships, future interviews, health, and severance packages. Available here and by RSS on September 11.
Coaching services
I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.
Get the ebook!
Past issues of Point Lookout are available in six ebooks:
- Get 2001-2 in Geese Don't Land on Twigs (PDF, )
- Get 2003-4 in Why Dogs Wag (PDF, )
- Get 2005-6 in Loopy Things We Do (PDF, )
- Get 2007-8 in Things We Believe That Maybe Aren't So True (PDF, )
- Get 2009-10 in The Questions Not Asked (PDF, )
- Get all of the first twelve years (2001-2012) in The Collected Issues of Point Lookout (PDF, )
Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info
Follow Rick
Recommend this issue to a friend
Send an email message to a friend
rbrenyrWpTxHuyCrjZbUpner@ChacnoFNuSyWlVzCaGfooCanyon.comSend a message to Rick
A Tip A Day feed
Point Lookout weekly feed