Volume 4, Issue 7;   February 18, 2004: Resuming Projects: Team Morale

Resuming Projects: Team Morale

by

Sometimes we cancel a project because of budgetary constraints. We reallocate its resources and scatter its people, and we tell ourselves that the project is on hold. But resuming is often riskier, more difficult and more expensive than we hoped. Here are some reasons why.

Looking around the room, Trish saw that her presentation was in trouble. Whether it was the slide on risks, or the one on budget, she knew that people were uncomfortable with her projections. The Gang of Six would probably follow Warren's lead, and Warren was unhappy.

Resuming projects is risky,
in part, because we
underestimate the risks
of rebuilding a team
"From what I see," he said, "starting from scratch might be better than picking up where we left off. You agree?"

Trish was ready. "The operative word is 'might,'" she began. "Resuming projects isn't our strong suit. Our estimates are soft. So yes, it might be better to start over. And it might not. My estimate is that starting over would cost between 90 and 125% of the cost of resuming. But, then, the result would be cleaner and more current. It's a tough call."

Tape recorder AKAI GX-260D

AKAI GX-260D tape recorder, which has a pause function. Photo by Erkaha CC BY-SA 4.0 via Wikimedia Commons.

Warren wasn't satisfied. "But how could that be? We've spent — let's see — 8.3? — on this so far! How could it be cheaper to start over? And why can't you answer with a simple 'yes, it will be cheaper' or 'no, it won't'?"

Trish, Warren, and the Gang of Six are struggling with one of the great paradoxes of project management: Resuming a paused project can cost more than starting over. The paradox lies in the conflict between the reality of the paused project and our own mental models of what's involved.

One part of this conflict lies in the special challenge of team formation for a resuming project. For various reasons, team rebuilders usually try to recruit former team members, and that creates special problems. Here are some reasons why:

  • Many have difficult memories of the project from the period just before cancellation.
  • Many may have "moved on" to success elsewhere in the organization.
  • Many are no longer employed within the organization, and even if they're willing to be rehired, rehiring policies often present obstacles.
  • Current managers of former team members might not permit them to rejoin the team, or they might attach difficult conditions to their release.
  • Selectivity in re-recruiting by team rebuilders can create resentments about the exclusion of some former team members and the inclusion of others.

These factors threaten team morale. Some mitigation tactics are possible:

  • Educate the team rebuilders about the difficulties they can expect when they try to reassemble the team, and how to address those difficulties.
  • Provide strong, public, and unambiguous support from top management.
  • Conduct a retreat for the whole team, facilitated by experts in team re-formation, to deal with the challenges.

When these tactics are available, safe conversations about taboo subjects are possible, and those conversations help overcome any ambivalence about (or opposition to) the resumed project. Without these tactics, you might be resuming not only a project, but a mass of problems, too. Go to top Top  Next issue: When You Need a Lift  Next Issue

Rick BrennerThe article you've been reading is an archived issue of Point Lookout, my weekly newsletter. I've been publishing it since January, 2001, free to all subscribers, over the Web, and via RSS. You can help keep it free by donating either as an individual or as an organization. You'll receive in return my sincere thanks — and the comfort of knowing that you've helped to propagate insights and perspectives that can help make our workplaces a little more human-friendly. More

Your comments are welcome

Would you like to see your comments posted here? rbrenfHlRlTgqCIXkUHBTner@ChacrEuHRQPYVKkOucGfoCanyon.comSend me your comments by email, or by Web form.

About Point Lookout

This article in its entirety was written by a 
          human being. No machine intelligence was involved in any way.Thank you for reading this article. I hope you enjoyed it and found it useful, and that you'll consider recommending it to a friend.

This article in its entirety was written by a human being. No machine intelligence was involved in any way.

Point Lookout is a free weekly email newsletter. Browse the archive of past issues. Subscribe for free.

Support Point Lookout by joining the Friends of Point Lookout, as an individual or as an organization.

Do you face a complex interpersonal situation? Send it in, anonymously if you like, and I'll give you my two cents.

Related articles

More articles on Project Management:

The Japanese battleship Yamato during machinery trials 20 October 1941Durable Agreements
People at work often make agreements in which they commit to cooperate — to share resources, to assist each other, or not to harm each other. Some agreements work. Some don't. What makes agreements durable?
A fancy diagram of the kind that often accompanies management fadsWhy Do Business Fads Form?
The rise of a business fad is due to the actions of both its advocates and adopters. Understanding the interplay between them is essential for successful resistance.
The breech plug of one of the nine 16-inch guns of the U.S.S. Missouri6
The Eisenhower Matrix is useful for distinguishing which tasks deserve attention and in what order. It helps us by removing perceptual distortion about what matters most. But it can't help as much with some kinds of perceptual distortion.
A Strangler Fig in AustraliaProjects as Proxy Targets: I
Some projects have detractors so determined to prevent project success that there's very little they won't do to create conditions for failure. Here's Part I of a catalog of tactics they use.
An empty officeAnticipating Absence: Why
Knowledge workers are scientists, engineers, physicians, attorneys, and any other professionals who "think for a living." When they suddenly become unavailable because of the Coronavirus Pandemic, substituting someone else to carry on for them can be problematic, because skills and experience are not enough.

See also Project Management and Project Management for more related articles.

Forthcoming issues of Point Lookout

Someone got the wrong information about which sneakers to wear on which feetComing April 30: On Planning in Plan-Hostile Environments: II
When we finally execute plans, we encounter obstacles. So we find workarounds or adjust the plans. But there are times when nothing we try gets us back on track. When this happens for nearly every plan, we might be working in a plan-hostile environment. Available here and by RSS on April 30.
A dramatization of a mobbing incidentAnd on May 7: Subject Matter Bullying
Most workplace bullying tactics have analogs in the schoolyard — isolation, physical attacks, name-calling, and rumor-mongering are common examples. Subject matter bullying might be an exception, because it requires expertise in a sophisticated knowledge domain. And that's where trouble begins. Available here and by RSS on May 7.

Coaching services

I offer email and telephone coaching at both corporate and individual rates. Contact Rick for details at rbrenfHlRlTgqCIXkUHBTner@ChacrEuHRQPYVKkOucGfoCanyon.com or (650) 787-6475, or toll-free in the continental US at (866) 378-5470.

Get the ebook!

Past issues of Point Lookout are available in six ebooks:

Reprinting this article

Are you a writer, editor or publisher on deadline? Are you looking for an article that will get people talking and get compliments flying your way? You can have 500-1000 words in your inbox in one hour. License any article from this Web site. More info

Follow Rick

Send email or subscribe to one of my newsletters Follow me at LinkedIn Follow me at Bluesky, or share a post Subscribe to RSS feeds Subscribe to RSS feeds
The message of Point Lookout is unique. Help get the message out. Please donate to help keep Point Lookout available for free to everyone.
Technical Debt for Policymakers BlogMy blog, Technical Debt for Policymakers, offers resources, insights, and conversations of interest to policymakers who are concerned with managing technical debt within their organizations. Get the millstone of technical debt off the neck of your organization!
52 Tips for Resuming Paused ProjectsWhen you resume a paused project, are you frustrated by the politics? Learn techniques for leaders of resuming projects.
303 Secrets of Workplace PoliticsIs every other day a tense, anxious, angry misery as you watch people around you, who couldn't even think their way through a game of Jacks, win at workplace politics and steal the credit and glory for just about everyone's best work including yours? Read 303 Secrets of Workplace Politics!
101 Tips for Effective MeetingsLearn how to make meetings more productive — and more rare.
Ebooks, booklets and tip books on project management, conflict, writing email, effective meetings and more.
Comprehensive collection of all e-books and e-bookletsSave a bundle and even more important save time! Order the Combo Package and download all ebooks and tips books at once.
If your teams don't yet consistently achieve state-of-the-art teamwork, check out this catalog. Help is just a few clicks/taps away!